Food service
Burger King, Orion Belagavi
A food court unit with no gas supply, a fully electric kitchen, and a mall opening date fixed before shell handover.
- 1150Sqft
- 09Weeks shell to trading
- 165kW connected load
- 02Weeks saved upstream
- 00Days late
01 · The shell we were given
An all electric kitchen doubles the load and moves the whole problem upstream.
The food court allocation had been set on the assumption of a gas-fired kitchen. An all-electric line roughly doubles the connected electrical load and changes the extract and make-up air balance with it.
The opening date was published before the shell was handed over. Anything that needed a new mall service application had to be resolved in the first fortnight or it would have consumed the programme outright.
Fig. 01 · Week 0, as handed over
02 · What we did not build
What we did not build
Three routes out of the load problem. Two were closed before mobilisation.
01 · Rejected
Apply for gas
Mall policy did not permit a new food-court gas connection. Even if it had, the application alone would have eaten six weeks of a nine week programme.
02 · Rejected
Cut the menu
A reduced equipment line would have fitted the original allocation comfortably. It also meant opening a store that could not serve the brand's full national menu.
03 · Built
Revise the allocation
Heat load and electrical load workbooks were produced before handover and taken to the mall directly. The allocation was revised while the box was still empty. Full menu, no programme impact.
03 · Programme achieved
9 weeks, shell to trading
Weeks · Ochre bars are on the critical path
04 · Trading
Traded from the mall's published opening day with the full national menu and no temporary equipment.
05 · Record
- Client
- Restaurant Brands Asia
- Location
- Belagavi
- Scope
- Design and build, food court unit
- Area
- 1,150 sqft
- Programme
- 9 weeks
- Completed
- January 2026